The industrial park model is formed and developed in association with the context and requirements of the periods of implementation of the economic development strategy. According to a report by the Department of Management of Economic Zones, Ministry of Planning and Investment (now the Ministry of Finance), as of July 2024, Vietnam has 301 industrial parks ("IPs") that have been put into operation, attracting a large amount of investment capital,[1] especially capital inflows from foreign direct investors.

Vietnam – Singapore Industrial Park Joint Venture Company Limited (VSIP). Source: CafeF
In this article, we will provide necessary information for investors when investing in industrial zones in Vietnam, and at the same time provide some recommendations and suggestions, contributing to supporting and guiding investors to comply with the provisions of the law on investment and other relevant legal regulations.
1. Forms of investment in industrial parks in Vietnam
According to the provisions of Decree 31/2021/ND-CP, investors can implement investment projects in industrial parks through the following activities:[2]

2. Order of investment procedures
|
Work done |
Contents of implementation |
Implementing unit |
|
INVESTMENT PREPARATION STAGE AND ESTABLISH A BUSINESS |
||
|
Investment Registration[3] |
|
Management Board of Export Processing and Industrial Zones[4] |
|
Business Registration |
|
Department of Finance[5] |
|
Engraving the mark |
|
Investors |
|
Registration of tax and social insurance information |
|
|
|
Open a bank account |
|
|
|
Announcement of business establishment |
|
Department of Finance |
|
PROJECT IMPLEMENTATION PHASE |
||
|
Land lease assignment |
Guidance on making cadastral maps of land lease and handover of GPS landmark pile locations |
Infrastructure Development Company |
|
Measurement and mapping of cadastral land lease |
Units of measurement |
|
|
Signing the Land Lease Contract |
Infrastructure Development Company |
|
|
Handing over land on the field to investors |
Infrastructure Development Company |
|
|
Preparation for construction investment |
Management Board of Export Processing and Industrial Zones [14] |
|
|
Appraisal and approval of master planning/ detailed planning for construction of construction investment projects |
Management Board of Export Processing and Industrial Zones [15] |
|
|
Appraisal of the feasibility study report on project construction investment (and at the same time appraisal of fire protection design according to the provisions of Point b, Clause 1, Article 17 of the Law on Fire Prevention and Fighting, Rescue and Rescue)[16] |
Management Board of Export Processing and Industrial Zones[17]/ Investors |
|
|
Appraisal and approval of fire protection (appraisal contents as prescribed at Point d, Clause 1, Article 17 of the Law on Fire Prevention and Fighting, Rescue and Rescue) |
Fire and Rescue Police[19] |
|
|
Project approval[20] |
Investors |
|
|
Design approval after basic design[21] |
Investors |
|
|
Issuance of construction permits (in case of failure to appraise the project construction investment feasibility study report) |
Management Board of Export Processing and Industrial Zones [22] |
|
|
Construction of works |
|
Investors Management Board of Export Processing and Industrial Zones / Department of Construction |
|
The project was completed and put into use |
Acceptance of fire prevention and fighting[23] |
Investors[24] |
|
Inspecting the acceptance of completed items and works to be put into operation and use (specialized construction agencies shall assume the prime responsibility for, and coordinate with the Police agencies in, inspecting the acceptance of fire protection) according to Article 24 of Decree 06/2021/ND-CP, Decree 175/2024/ND-CP of the Government detailing a number of articles and measures for the implementation of the Law on Construction, Decree 35/2023/ND-CP of the Government amending and supplementing a number of articles of Decrees in the field of state management of the Ministry of Construction, Decree 144/2025/ND-CP of the Government regulating the delimitation of competence of local governments at 02 levels in the field of state management of the Ministry of Construction |
Management Board of Export Processing and Industrial Zones / Department of Construction / Fire Protection Agency[25] |
|
|
Environmental license (for cases where an environmental impact assessment report must be made) |
Management Board of Export Processing and Industrial Zones[26] |
|
|
Trial operation of waste treatment works (if any) |
Investors[27] |
|
|
OPERATIONAL PHASE |
||
|
Labour |
|
Department of Home Affairs[28] |
|
Registration of compulsory social insurance, health insurance and unemployment insurance |
Social Insurance |
|
|
Business Activities |
|
Department of Industry and Trade and specialized management agencies |
|
Periodic Reports |
Implement the regime of periodic reporting as prescribed, including:
|
|
|
Ownership of land-attached assets |
Certificate of ownership of land-attached assets |
Provincial People's Committees[35] |
|
Maintenance of construction works |
Maintenance of construction works, construction machinery and equipment |
Investors[36] |
|
Invest |
Carry out procedures for adjustment of investment projects in case the project has changed contents compared to those registered in the Investment Registration Certificate |
Management Board of Export Processing and Industrial Zones [37] |

[1] https://www.mpi.gov.vn/portal/Pages/2024-8-23/Phat-trien-khu-cong-nghiep-va-mo-hinh-khu-cong-ngh0qfsuf.aspx, accessed 2025/09/26
[2] Article 62 of Decree 31/2021/ND-CP.
[3] Article 37.1 of the Law on Investment 2020
[4] Article 34.3 of Decree 31/2021/ND-CP
[5] Article 20.1 of Decree 168/2025/ND-CP
[6] Article 43 of the Law on Enterprises 2020
[7] Article 8.1 of Decree 168/2025/ND-CP
[8] Article 8.10 of Decree 168/2025/ND-CP
[9] Article 32.2 of the Law on Tax Administration 2019.
[10] Article 73 of Decree 168/2025/ND-CP
[11] Article 32.3 of the Law on Enterprises 2020
[12] Article 68.3(d) of Decree 35/2022/ND-CP
[13] Article 68.3(d) of Decree 35/2022/ND-CP
[14] Article 35 of the Law on Environment 2020
[15] Article 68.2(c) of Decree 35/2025/ND-CP
[16]Article 68.2(c) of Decree 35/2025 and Article 121.5(dd) of Decree 175/2024/ND-CP
[17] Article 68.2(c) of Decree 35/2025 and Article 121.5(dd) of Decree 175/2024/ND-CP
[18] Article 57.4(b) of Decree 175/2024 and Article 1.14 of the Law on Construction 2020
[19] Article 9 of Decree 105/2025/ND-CP
[20] Article 72.1 of the Law on Construction 2014 and Article 22.1 of Decree 175/2024/ND-CP
[21] Article 82.3(c) of the Law on Construction 2014, Article 1.24. (8) The Law on Construction amended 2020 and Article 43.1 of Decree 175/2024/ND-CP.
[22] Article 68.3(b) of Decree 35/2022/ND-CP
[23] Article 8.1 of Decree 105/2025/ND-CP
[24] Articles 18.1 and 18.2 of the Law on Fire Prevention and Fighting and Rescue 2024
[25] Article 18.4 and Article 18.5 of the Law on Fire Prevention and Fighting and Rescue 2024
[26] Article 68.3(d) of Decree 35/2022/ND-CP
[27]Article 31 of Decree 08/2022/ND-CP
[28] Decree 219/2025/ND-CP
[29] Article 9 of Decree 09/2018/ND-CP
[30] Article 72.2(a) of the Law on Investment 2020 and Article 102 of Decree 31/2021/ND-CP
[31] Articles 70 and 100 of Decree 29/2021/ND-CP
[32] Article 68.2(l) of Decree 35/2022 and Article 110.7 of Circular 200/2014
[33] Article 66.5 of Circular 02/2022/TT-BTNMT.
[34] Article 68.2(d) of Decree 35/2022/ND-CP.
[35] Article 136.1(a) of the Land Law 2024.
[36] Article 126 of the Law on Construction 2014.
[37] Article 68.3(b) of Decree 35/2022/ND-CP.